Absolute impossiblity to recover state aid: the SNCM/CMN case
It
is settled case law that the EU Courts are unwilling to accept the
absolute impossibility to recover state aid defence submitted by
Member States that have been found by the European Commission to have
granted aid in breach of the provisions of the TFEU. EU Courts have
indeed adopted a strict interpretation of the concept of
impossibility. As a result, to demonstrate to the expected
evidentiary standard the impossibility to implement the Commisssion'
s decision can be an insurmountable task for a Member States adressee
of a recovery order.
Unsurprisingly
in light of the above, the Court of Justice of the EU (CJEU) has
recently rejected the pleadings submitted by France, arguing for the
impossibility to recover aid previously granted to two ferry
companies, SNCM and CMN (CJEU, judgment of 9 July 2015 made in the
Case C-63/14 European Commission v France).
Following
receipt a complaint filed by a competitor, the Commission launched an
investigation into the public service delegation contracts awarded to
SNCM and CNM. By these contracts SNCM and CMN committed to operate
for the 2007-2013 period a number of maritime links from the port of
Marseille to some Corsican ports and viceversa with the view to
guarantee the territorial continuity between mainland France and
Corse. By the decision made in May 2013 the Commission found that the
compensation awarded to SNCM and CMN for the provision of the above
maritime links constituted illegal and incompatibility aid and
ordered France to recover it (European Commission, Decision
2013/435/EU of 2 May 2013, Case SA.22843,
Lignes maritimes Marseille-Corse opérées par la SNCM et la CMN).
France
and SNCM challenged the Commission's decision before the General
Court of the EU (GC). The appeals are still pending before the GC
(Case T-366/13 France v Commission; Case T- 454/13, SNCM v
Commission). The GC also rejected the France application for interim
measures for the suspension of the challenged decision.
In
the meantime, believing that France failed to implement the negative
decision of the Commission of 2 May 2013, in February 2014 the
Commission brought an infringement action before of CJEU on the basis
of Article 108(2) TFEU. To its defence, among other things, France
played the card of the absolutely impossibility to execute the
Commission's recover order. It contended that the impossibility was
due to the social unrest and the break in the territorial continuity
that would occur had SNCM given back the aid it had received before.
Indeed, SNCM was alrealy placed by the Commercial Court of Marseille
in a court-supervised administration procedure as it had failed to
repay a loan. Therefore, so the France argument run, the
implementation of the recover order would result in the insolvency
and in the following compulsory liquidation of SNCM, with the ensuing
risks of social unrest. France also argued that the exit of SNCM from
the market would make necessary to conclude a public service
delegation contract with another ferry company that might not have
the means to operate the required maritime links. As a consequence,
in the period between the termination of the contract with SNCM and
the point in time when the new awardee would start its services, the
maritime links in such contract and, accordingly also the territorial
continuity between Marseille and Corsica, would be likely suspended.
The
CJEU rejected all the France's contentions. It pointed out that when
social unrest is feared Member State have to to adopt all the
suitable measures to guarantee the full scope and effect of EU law so
to ensure its proper implementation. It is upon Member State to
demonstrate that it is not possible to deal with problems for public
order with the means at their disposal. The CJEU found that France
did not provide such evidence. The possible long-term blockade of the
maritime links with Corse evoked by France as an effect of the
recovery of aid could no be taken as decisive evidence of the
impossibility to implement the decision. As made clear by the AG
Wathelet in his Opinion, a similar situation was already faced by
French authorities at the time of the protacted strike in 2005 that
blocked some links between mainland France and in Corsica. And then
France succeeded in supplying Corsica through alternative ways. In
addition, the CJEU also noticed that the preliminary actions taken by
France to recover aid did not cause any social unrest.
As
for the risk of break of territorial continuity, the CJEU believed
that with the SNCM xit of the market, at least in a short-time
horizon the Marseille-Corse maritime links would be reduced. Yet, it
held that France would not give any evidence that this event might
have consequences of such magnitude on public order that, as a
result, the recovery of aid should be regarded as absolutely
impossible. As said before, the measures taken to deal with the 2005
strike indicated that the French authorities could rely on measures
suitable to cope with the consequences on public order of such
event.
In
conclusion, in European Commission v France the CJEU
did not depart from its strict approach to assess the absolute
impossibility defence. Outbreaks of social unrest feared due to the
implementation of recovery order are not considered as evidence of
impossibility of such recovery, unless the addresee Member State
demonstrates to not have at its disposal suitable measures to deal
with the public order problems. Something more than political
disconfort in taking action against groups opposing to the recovery
order is then needed in order to meet the evidentiary burden for the
granting of the absolute impossibility defence.
European
Commission v France also made clear that practical difficulties
in replacing the previous awardee of a public service contract, that
would exit the market due to the repayment of illegal aid it had
received, may not be considered a a ground of impossibility of
recovery. This was not the case with aid granted to SNCM, considering
that the French authorities could rely on alternative channels to
ensure the maritime links that the beneficiary aid had to operate.
Comments