The EFTA Surveillance Authority clears a PSO compensation in the maritime sector on the basis of the Altmark doctrine
Applying the Altmark doctrine to the case The Coastal Route Contracts Bergen-Kirkenes
(Decision of 16 August 2018 no 072/18/COL) the EFTA Surveillance Authority (the
ESA) has ruled out that a public service compensation paid by Norway for the
provision of maritime links constituted State aid.
Following guidance given by the Authority in the
previous Hurtigruten case (Decision
no. 70/17/COL) the Norwegian contracting authorities divided the contract for
the provision of the so-called Coastal Route links into three different
packages with a 10-year entrustment period. The maritime links to be provided
by the awardees was qualified as a public service obligation (PSO). And the
compensation to be paid to the providers of these PSO was found by the ESA to
meet all the four conditions for the application of the Altmark doctrine.
First Condition- Clearly defined PSO
In the ESA view, the PSO compensation granted to the
awardees, Hurtigruten and Havila, constitutes compensation for clearly defined services
of general economic interest (SGEI). Indeed, the contracting authorities clearly
set out the various requirements to be met by the service providers, including
the requirement for reserve capacity that was necessary and proportionate to a
real public service need.
Second Condition- Prior determination
of the parameters of the PSO compensation
The methods to calculate the PSO compensation were
defined in a clear and transparent manner in the contracts concluded with Hurtigruten
and Havila, which then met the Second Condition. In particular, the contracts distinguished
costs related to the capacity and sailing pattern from the costs and revenues
related to passengers, and costs and revenues related to cargo transport.
Third Condition- No overcompensation
The Norwegian contracting authorities have correctly
calculated the PSO compensation by employing a cost and revenue methodology. Because
Hurtigruten and Havila used their vessels also for commercial activities in addition
to the PSO, the contracting authorities require them to keep separate accounts.
In this way, it was possible to register the costs and revenues directly
associated to the discharge of the PSO and assess them in transparent and
objective manner. The ESA also held that the expected 9% return on capital
agreed between the contracting authorities and the awardees was a reasonable
profit on public service activities.
Fourth Condition- The public
procurement process
In this case, the Norwegian authorities opted for a
negotiated procedure to select the providers of the tendered out SGEI. The ESA
stated that the contracting authorities shaped this negotiated procedure so
that it had a competitive nature. The ESA praised the Norway authorities for
splitting up the Coastal Route services in three smaller packages because this
option opened up the market to more operators and perhaps attracted more than
one bidder. All the bidders participated in a single procurement procedure and
could make offers for one or more packages but they did not have access to
information concerning competing bidders.
Though negotiated procedures imply a certain margin of
discretion for contracting authorities in assessing the bids placed by tenderers,
the ESA took the position that the procedure designed by the Norwegian authorities
enabled them to select the operator capable of providing the service in
question at the least cost to the community. All the selection and award criteria
were set out in advance in the tender notice, greatly limiting the discretion
of the Norwegian authorities. The compensation adjustment clause inserted in
the contract entered into with Hurtigruten was within the scope of negotiations
aimed at reducing the level of the PSO compensation. Moreover, the Norwegian
authorities imposed strict conditions for the application of the clause.
In light of the above, the ESA found that the PSO
compensation in question met the four-limb test for the application of the Altmark doctrine and, accordingly, did
not confer an advantage on Hurtigruten and Havila. As a result, these national
measures did not constitute State aid within the meaning of Article 61(1) of
the EEA Agreement.
Final remarks
The ESA decision in The Coastal Route Contracts Bergen-Kirkenes case is worth reading for
it ruled out that a PSO compensation constituted a State aid on the basis of
the Altmark doctrine. Importantly, the national measures notified by Norway to
the ESA met all the four conditions of the application of the doctrine,
including the much controversial Fourth Condition. The Coastal Route Contracts Bergen-Kirkenes gives guidance on which
steps national authorities. that opt for a negotiated procedure to select to whom
entrust a public mission. have to take to comply with the Fourth Altmark
Condition. The competitive tender procedure was preceded by a preliminary
market consultation with potential suppliers to stimulate their interest in the
competition that resulted in three participating in the ensuing tender process.
The crucial factor in The Coastal Route
Contracts Bergen-Kirkenes case was that the contracting authorities clearly
set out in the tender notice the selection and award criteria limiting from the
outset their discretion. In spite of the negotiations entailed by the tender
procedure called for by the Norwegian authorities, they still select the awardee
of the public service contracts at the least costs to the community.
Comments